A. Vertical installation, switch frame, closing mechanism, cable sheath, and protective steel pipe should all be reliably grounded (not connected in series).
B. Before operation, several no-load opening and closing operations should be carried out, with no jamming in the rotating parts, the closing in place, and sufficient safety distance after opening.
C. The fuse used in series with the load switch should be selected appropriately, that is, when the fault current is greater than the breaking capacity of the load switch, the fuse should be melted first, and then the load switch can be opened.
D. When closing, the contact is good, and there is no overheating phenomenon at the connection part. During inspection, attention should be paid to checking the porcelain bottle for dirt, cracks, porcelain falling off, and flashing discharge; The switch cannot be flushed with water (indoor type). When a high-voltage cabinet controls a transformer, it is best to shut down the high-voltage cabinet of the circuit by replacing the fuse